Cardinals Stadium Construction 45 Percent Complete

CatBoxBackFan

Hall of Famer
Joined
Sep 18, 2002
Posts
1,670
Reaction score
102
Location
Margaritaville,north of Tucson
Cardinals Stadium Construction 45 Percent Complete: Northern Half of Roof Assembled





GLENDALE, Ariz. (Nov. 12, 2004) -- Construction work at the new Arizona Cardinals Stadium has reached the 45 percent completion mark with the assembly of the northern half of the retractable roof.

The northern-most half of the retractable roof structure has been completed at the ground level allowing workers to continue structural concrete work at the southern end of the building. Assembly on the southern half has begun with the East Brunel Truss scheduled for completion by Christmas and the West Brunel Truss to be completed in January. The retractable roof components have been installed along with the steel roof material. The translucent weatherproof fabric that will stretch over the retractable roof panels will be added later.

The 700-foot long trusses will support the roof. Each truss is 87 feet high at its tallest point and weighs about 1,800 tons. Brunel’s truss design is credited with allowing long, uninterrupted expanses to be bridged.

All concrete pours have been completed for the Main Concourse and the Club Level. The concrete slab has also been completed for the Suite Level on the western side of the stadium.



More than 70,000 yards of concrete have been poured so far out of the 82,000 yards of structural concrete to be poured at the new stadium. The structural concrete work is expected to be completed by Christmas. There will be a total of 96,000 yards of concrete poured in the stadium portion of the project.



Three of the six chillers have been set at the southeastern portion of the stadium along with the cooling towers. The remaining three chillers will be set later this month.



By Thanksgiving three out of the four Super Columns will have been completed.



Looking Ahead



November – Assembly of southern truss halves
As work continues to finish the south and west sides of the concrete structure -- making a complete bowl -- workers have started assembling the southern halves of the two Brunel trusses on the south end of the stadium floor. Building them in this manner is safer and more efficient when at ground level than when suspended overhead.

December – Completion of structural concrete
The entire concrete frame is expected to be completed around Christmas. At this point, the bowl structure will be finished. Inside the oval-shaped bowl, workers will be close to finishing the assembly of the Brunel trusses for the roof with completion expected in January. The trusses will be assembled in such a way that the ends of each will fit snuggly in concrete channels in the building’s Super Columns. The channel will help guide the trusses into place when they are hoisted to the top of the stadium later in February.



The new Cardinals Stadium will be completed in August 2006 and will host the BCS Championship Game in 2007 and the Super Bowl in 2008. For more information on the stadium, go to www.az-sta.com.
 

Jim O

Registered User
Joined
Sep 4, 2002
Posts
5,838
Reaction score
9
Location
Tempe, AZ
You must be registered for see images

View of steel roof components installed on northern half of roof.
 

Jim O

Registered User
Joined
Sep 4, 2002
Posts
5,838
Reaction score
9
Location
Tempe, AZ
You must be registered for see images

The northeast corner of the stadium shows the installation of the metal skin.
 

Jim O

Registered User
Joined
Sep 4, 2002
Posts
5,838
Reaction score
9
Location
Tempe, AZ
You must be registered for see images

Aerial view showing partially completed components on northern most half of roof.
 

Jim O

Registered User
Joined
Sep 4, 2002
Posts
5,838
Reaction score
9
Location
Tempe, AZ
You must be registered for see images

View looking north through the slot towards the northern half of the roof.
 

CardinalLaw

Registered User
Joined
Sep 12, 2004
Posts
1,926
Reaction score
0
Cool Pics. Thanks Jim O. I can't wait for it to get done.
 

okcardzona

LEGACY MEMBER
LEGACY MEMBER
Joined
Mar 9, 2003
Posts
698
Reaction score
4
Location
Oklahoma city
them pictures gives me goosebumps. I have never seen anything so beautiful.
Thanks to the voters of the great state of Arizona
 

MrY

Veteran
BANNED BY MODERATORS
Joined
Oct 17, 2002
Posts
476
Reaction score
0
A golf buddy of mine who is a pilot flew over the stadium Thurs and called to tell me how awesome it looks from the air....
 

Redheart

Stack 'em up!
Joined
Aug 9, 2002
Posts
4,391
Reaction score
3
Location
Mesa
This time of year...

I don't mind games at SDS at all...but THAT is going to be one GREAT place to watch the CARDINALS!
 

ANDY440

Registered
LEGACY MEMBER
Joined
Oct 8, 2004
Posts
1,176
Reaction score
30
Location
Mesa
I forget,is it going to have a retractable roof like Bank One ?
 

joeshmo

Kangol Hat Aficionado
Joined
Feb 23, 2004
Posts
17,247
Reaction score
1
adny440 said:
I forget,is it going to have a retractable roof like Bank One ?

:shrug: ;)

CatBoxBackFan said:
GLENDALE, Ariz. (Nov. 12, 2004) -- Construction work at the new Arizona Cardinals Stadium has reached the 45 percent completion mark with the assembly of the northern half of the retractable roof.

The northern-most half of the retractable roof structure has been completed at the ground level allowing workers to continue structural concrete work at the southern end of the building. Assembly on the southern half has begun with the East Brunel Truss scheduled for completion by Christmas and the West Brunel Truss to be completed in January. The retractable roof components have been installed along with the steel roof material. The translucent weatherproof fabric that will stretch over the retractable roof panels will be added later.
 

Skkorpion

Grey haired old Bird
LEGACY MEMBER
Supporting Member
Joined
May 9, 2002
Posts
11,026
Reaction score
5
Location
Sun City, AZ
I moved to Peoria, AZ and I pass by that sucker every other day. It takes between 14 to 17 minutes to get to the northern 101 exit that leads to the stadium. I'm ready to go tailgate in the mud right now.

The only thing I wonder about is whether the designers have made the second tier steep enough. Denver's second tier is mountain goat-steep, making all those seats closer to the field and giving them great views.
 
OP
OP
CatBoxBackFan

CatBoxBackFan

Hall of Famer
Joined
Sep 18, 2002
Posts
1,670
Reaction score
102
Location
Margaritaville,north of Tucson
Skkorpion said:
I moved to Peoria, AZ and I pass by that sucker every other day. It takes between 14 to 17 minutes to get to the northern 101 exit that leads to the stadium. I'm ready to go tailgate in the mud right now.

The only thing I wonder about is whether the designers have made the second tier steep enough. Denver's second tier is mountain goat-steep, making all those seats closer to the field and giving them great views.

Here a pic of the upper bowl seating


You must be registered for see images
 

phillycard

ASFN Addict
Joined
Aug 22, 2003
Posts
7,303
Reaction score
4,314
Location
The 215
CatBoxBackFan said:
Here a pic of the upper bowl seating


You must be registered for see images


I can already see me leaning over the edge with a brew in my hand cheering ANOTHER Cards touchdown! :D
 
Last edited:

azdad1978

Championship!!!!
Joined
Dec 8, 2002
Posts
14,982
Reaction score
50
Location
ordinance 2257
I pass by the new stadium everyday and let me tell you guys that its giving me goosebumps knowing this place will be rocking and rolling in 2006!!! :thumbup:
 

Latest posts

Members online

Forum statistics

Threads
557,642
Posts
5,448,705
Members
6,335
Latest member
zbeaster
Top