Raising the roof

CatBoxBackFan

Hall of Famer
Joined
Sep 18, 2002
Posts
1,670
Reaction score
102
Location
Margaritaville,north of Tucson
3 days, 5,600 tons; Cards Stadium about to get its cover

Pat Flannery
The Arizona Republic
Feb. 18, 2005 12:00 AM

The "gee whiz" moment in the building of Cardinals Stadium occurs this weekend when 120 engineers, steel workers and specialized equipment operators finally put a lid on the $370.6 million venue.

Mammoet, a Dutch company specializing in heavy lifts, will fire up its high-tech gadgets this morning, kicking off a carefully choreographed three-day operation to hoist the stadium's 5,600-ton retractable roof structure - that's 11.2 million pounds of steel - into place high above the field.

"We believe it's the heaviest lift ever in North America," said Brad Parker, an Arizona Sports and Tourism Authority spokesman.



The lift is another milestone in the stadium's development. Once the roof is finished and sealed later this year, work will migrate inside and passers-by on Loop 101 won't notice the changing construction landscape nearly as often as they once did. The stadium should be weatherproof by November.

Despite an unusually wet winter, construction is still on schedule for the stadium to open in August 2006. Rain this weekend should not deter the lift, though it could be delayed if high winds or lightning are present.

Designers planned for this weekend's lift for several years, building four concrete supercolumns into the bowl specifically to bear the weight of the lift and hold the roof's gigantic trusses in place until the rest of the roof-support system is in place.

Even the stadium bowl was built in sections like a pie, rather than by the usual level-at-a-time circular method, to accommodate the trusses. The unusual construction method freed up space inside the stadium so the trusses could be built there, near ground level, instead of high above the bowl.

Construction manager Charlie Prewitt of Hunt Construction Group said piecing together the roof's skeleton in this way was safer, easier and cheaper, and it happened sooner than otherwise would have been possible. Now, it has to be lifted into place.

Its central features are two 700-foot-long Brunel trusses that were assembled section by section starting last August. The length of three Boeing 747 jets parked end to end, these jumbo eye-shaped trusses weigh 1,770 tons apiece and had their tapered ends built into vertical slots in the concrete supercolumns that will help support them. Retractable roof panels are now attached securely atop the parallel arcs, stabilizing them for the lift.

Each 12- by 17.5-foot supercolumn has a yellow steel frame atop it that houses two all-important strand jacks. The frames are easily visible to cars passing on Loop 101.

Through each jack are threaded 54 steel cables, or "strands," that extend down through the slot in the supercolumn and attach to the end of a Brunel truss. That means each end of a Brunel truss will have two jacks and 108 cables pulling it upward through the slot toward the jacks.

For today's initial liftoff, the Brunel trusses will be unbolted from steel support posts and guy lines propping them up on the field. The hydraulic jacks, synchronized by computer and operated from a control center on the upper concourse, then will take a small stroke.

Prewitt said the roof assembly initially will move just a few inches at a time. Then engineers will inspect, making sure everything is A-OK. The process will continue that way until the belly of each truss, the lowest point in its arc, clears support posts underneath.

"It's going to be like watching grass grow," Prewitt said. "The first couple of inches, it could take us an hour."

As their ends are pulled, the heavy trusses will flex like a hunting bow. Prewitt therefore estimates the jacks will have to lift the ends 6 to 7 feet before the belly of either truss clears its support posts. Once airborne, the trusses will be raised 1 1/2 more feet and left to hang under their own weight until 8 a.m. Saturday, when the real lifting begins.

Again, the jacks initially will take small strokes, with engineers making sure they are pulling at equal rates and keeping the hoisted steel level.

When engineers are confident everything is working as planned, the jacks will take increasingly large strokes until the roof is slowly rising 12 to 18 inches per stroke. The routine will stop periodically for inspections and laser measurements as engineers pore over computer data monitoring stress on the jacks, trusses and supercolumns. The concrete columns, for example, will bow slightly under the load's weight.

Seven to nine hours later, if all goes well, the roof will be at its highest point. The jacks will stop, and the roof again will hang overnight. On Sunday, workers will scale scaffolds around the supercolumns and maneuver four horizontal transfer girders into notches near the tops of the columns, bolting them in place. The roof then will be lowered a foot or two, bringing the ends of the Brunel trusses to rest atop the transfer girders.

Once the trusses settle into place, work will start in March to link smaller trusses from the top edge of the stadium bowl to the Brunel trusses. Those smaller trusses will support the rest of the roof's metal and rubberized decking.

When structural roof work is finished in late June, a tough, specialized fabric known as Birdair will be stretched over the skeletal frames of the retractable panels and other parts of the roof. In late fall, the retractable panels will open for the first time.

As complicated as the process seems, Prewitt said, it is one of Mammoet's simpler jobs.

"It's real amazing," Prewitt said. "When you think about it, this is about as simple a lift as you can do because you're taking it straight up."


AzCentral.com
 

Red Hawk Old

Veteran
Joined
Oct 23, 2004
Posts
106
Reaction score
0
Location
Buckeye
CatBoxBackFan said:
3 days, 5,600 tons; Cards Stadium about to get its cover

Pat Flannery
The Arizona Republic
Feb. 18, 2005 12:00 AM

Despite an unusually wet winter, construction is still on schedule for the stadium to open in August 2006. Rain this weekend should not deter the lift, though it could be delayed if high winds or lightning are present.


AzCentral.com

Skorp? Your pessimism isn't working. :D
 

Gee!

BirdGang
Supporting Member
Joined
Nov 17, 2003
Posts
26,222
Reaction score
25
Location
Gee From The G
Fox 10 has camera crews out there today. They said they would raise the roof a whopping 2 feet today, then let it settle. The roof will not actually on top till Tuesday morning.
 

azdad1978

Championship!!!!
Joined
Dec 8, 2002
Posts
14,982
Reaction score
50
Location
ordinance 2257
Gee! said:
Fox 10 has camera crews out there today. They said they would raise the roof a whopping 2 feet today, then let it settle. The roof will not actually on top till Tuesday morning.
As long as it gets up there its all good to me.
 

MadCardDisease

Moderator
Moderator
Supporting Member
Joined
May 13, 2002
Posts
20,798
Reaction score
14,744
Location
Chandler, Az
Cardinals Stadium Roof Lift Set for Weekend:
Heaviest Lift of its Kind Ever Accomplished in North America
GLENDALE, Ariz. (Friday, Feb. 18, 2005) – Crews are prepared to hoist the major portion of the retractable roof at the new Cardinals Stadium this weekend in what will be the largest single roof lift in North America. The center portion of the retractable roof weighing 5,500 tons will be hoisted to the top of the stadium.

The four-day process begins today (Friday) and is expected to be finished by Monday. The most dramatic part of the roof lift is when the structure is raised 156 feet above the stadium floor. Weather and other variables can affect the speed of the process which is carefully controlled by computers.

The 11 million pound roof section weighs the equivalent of 14 Boeing 747 airplanes and is being accomplished with eight strand lifting units capable of hoisting 990 tons each. The total capacity of the lifting system is 7,900 tons or enough to raise the Eiffel Tower.

The roof is set on the two giant Brunel trusses which are 87-feet tall and span 700 feet long. The corner of each Brunel truss is set into a channel on each of four Super Columns which were specifically engineered and designed to perform the lift. The lift is being managed by Hunt Construction Group, the nation's leading sports facility builder that has managed construction of four of the six retractable-roof stadiums in the U.S. including Bank One Ballpark in Phoenix.

The roof lift comes as the construction project passes the 50 percent completion mark, continuing to be on schedule for its opening in August of next year.

The Process

On Friday, workers begin to disconnect the Brunel trusses from the support posts on which they have been resting while the retractable roof was being assembled. Also, supporting guy wires are disconnected and the lift team raises the roof an initial 18 to 24 inches. Then the entire roof assembly is allowed to settle. Teams conduct inspections and tests throughout this time.

After inspectors give the go-ahead, the carefully planned, computer-controlled ascent of the roof begins. There will be frequent stopping points as inspection teams review progress. The roof assembly will be raised about 120 feet to a position about 156 feet above the stadium floor.

Concluding the lift, ironworkers will install transfer girders in the notches at the top of the Super Columns. The entire roof assembly will be lowered 18 to 24 inches, coming to rest on the transfer girders.

Future Milestones

March to July – Roof closure
Work begins to complete closure of the roof. While Brunel trusses support the retractable roof panels, a mix of structural steel, decking, rubberized roofing and a waterproof fabric will surround those retractable panels. The translucent fabric will allow natural light to pass through the roof while keeping heat and water out and the cool air in. The roof is expected to be complete in July.

May – Lower seating construction begins
The lower reaches of the stadium’s interior bowl, the part of the stadium nearest the field, starts construction. This includes installation of pre-cast concrete risers on which the lower bowl seats will rest. Work lasts through September.

July – Installation of the stadium’s event seating beings
Seating installation begins while work continues on masonry, electrical and mechanical rough-ins and lighting.

November – Exterior walls complete
Exterior walls of the stadium are completed, making the stadium weather tight. At this point, dry wall installation, painting, millwork and concession construction begins in the interior.

April 2006 – Field tray complete
Completion is expected on the unique moveable tray that will contain the stadium’s football turf. The huge tray will be built in its entirety outside the stadium and then the grass sod will be installed. It will not be rolled into the stadium from its south end until June. The field will be rolled inside the stadium only for game days, otherwise being kept outside where it can get plenty of air and sunshine. The turf tray will roll along steel rails on more than 400 steel wheels. Workers will have access to the wheels and the underside of the tray for maintenance and repair from a special work trench located near the southern end of the stadium.

August 2006 – Stadium complete and ready for occupancy in time for the Cardinals’ season.

January 2007 – Fiesta Bowl and BCS National Championship

January 2008 – Super Bowl XLII

The retractable roof is just one of the unique features of the stadium which will be the host of the Arizona Cardinals, the Tostitos Fiesta Bowl, the 2007 BCS Championships and the 2008 Super Bowl.

The 63,000-seat stadium will be able to be expanded to 73,000 seats and will feature North America’s first roll-out natural grass field. It will open in August of next year.

Cardinals Stadium Project Team

      • o Owner: Arizona Sports and Tourism Authority
        o Tenants: Arizona Cardinals, Tostitos Fiesta Bowl
        o Design Builder: Hunt Construction Group
        o Architects: HOK S+V+E in collaboration with Eisenman Architects
        o Roof Structural Engineer: Walter P. Moore
        o Stadium Structural Engineer: TLCP Structural
        o Roof Steel Fabricator/Erector: Schuff Steel
        o Roof Mechanization Contractor: Uni-Systems
 

Gee!

BirdGang
Supporting Member
Joined
Nov 17, 2003
Posts
26,222
Reaction score
25
Location
Gee From The G
azdad1978 said:
As long as it gets up there its all good to me.
True.

I guess I was thinking Im glad we didnt go tailgate to watch 2 feet of movement. :D
 

azdad1978

Championship!!!!
Joined
Dec 8, 2002
Posts
14,982
Reaction score
50
Location
ordinance 2257
Gee! said:
True.

I guess I was thinking Im glad we didnt go tailgate to watch 2 feet of movement. :D
That will be one wet tailgating with all the rain coming down for the whole weekend.
 

Avondale_Larry

Registered
Joined
Dec 11, 2003
Posts
231
Reaction score
0
Location
Avondale USA
I went over Friday at around noon. No discernable movement.

I went back today (Saturday) at around 11:00. There was a croud on 91st Ave, so it was somewhat hard to find a place to park. The roof is a third of the way to the top.

I'll post a picture later, assuming my brother who had the camera sends it to me.

L
 

Kel Varnsen

Moderator
Moderator
Supporting Member
Moderator Emeritus
Joined
Jun 28, 2003
Posts
33,369
Reaction score
11,994
Location
Phoenix
Avondale_Larry said:
I went over Friday at around noon. No discernable movement.

I went back today (Saturday) at around 11:00. There was a croud on 91st Ave, so it was somewhat hard to find a place to park. The roof is a third of the way to the top.

I'll post a picture later, assuming my brother who had the camera sends it to me.

L

Please do post pictures. I'm always so impressed with what engineers can do. I'm also curious to see what it looks like. How do they construct a roof inside the building itself and then raise it? Seems like it would be impossible to make it big enough.
 

CardinalChris

Big Man Himself
Joined
Jul 11, 2002
Posts
3,929
Reaction score
0
Location
Fresno, CA
Raise the roof? I'm there.......
 

Attachments

  • dj_mixerboard_turntables_raising_the_roof_lg_wm.gif
    dj_mixerboard_turntables_raising_the_roof_lg_wm.gif
    59.4 KB · Views: 341

Scott MS

Registered
Joined
Mar 8, 2004
Posts
4,144
Reaction score
15
Anybody have any pictures? I find it strange that the webcam is "down for maintenance" today, of all days!! I would have like to watch some of the roof going up.
 

TruColor

Trombonist in Roger Goodell's Wedding Rcpt.
Joined
May 13, 2002
Posts
4,148
Reaction score
3,097
Location
Prescott, AZ
I've been wondering if they took the webcam down in case there's a disaster; that way they wouldn't have a bunch of people watching...a la Miller Park circa 1998 or 1999.

Not trying to be pessimistic; just a wonderin'...
 

Red Hawk

JUST WIN!
Joined
Sep 13, 2002
Posts
1,911
Reaction score
0
Location
Buckeye, AZ / Section 106
Was there a little after 3 roof looked half way up.

Met a guy named John who was all decked out in Cards hard hat and apparel coming from the stadium. Apparently parked in the wrong lot instead of the security controlled one for the 'events'. Said the webcam was down because of obtruction with the observation tower. Said it would be working soon.

Pictures from today
You must be registered for see images

You must be registered for see images

You must be registered for see images

You must be registered for see images
 
Last edited:

Scott MS

Registered
Joined
Mar 8, 2004
Posts
4,144
Reaction score
15
PANTONE194C said:
I've been wondering if they took the webcam down in case there's a disaster; that way they wouldn't have a bunch of people watching...a la Miller Park circa 1998 or 1999.

Not trying to be pessimistic; just a wonderin'...


I actually thought the same thing -- Miller Park.
 

Wildfire

Registered
Joined
Aug 4, 2002
Posts
261
Reaction score
46
Location
Flower Mound, TX
Thanks for the photos, keep um coming.

Can't wait until my son, grand-son, and I make it to AZ for a game. Until then, look for us all proudly wearing our Cardinal gear with the Cards play in Dallas this year (We'll be in Houston this year too)
:wave: :thumbup:
 

PDXChris

All In!
Supporting Member
Banned from P+R
Joined
Mar 28, 2003
Posts
31,406
Reaction score
28,058
Location
Nowhere
I just drove buy, it looks amazing with all the lights, I wish I had my cmaera, from a distance it looks almost done and you can imagine a game going on with all the lights they have on
 

SouthNZoneFan

GOOD FOR ME TO POOP ON
Joined
Jul 30, 2004
Posts
1,898
Reaction score
0
I cannot wait to see it done. I come home in March and cannot wait to go and take a few photos. Keep them coming if you have them...

James
 

Jetstream Green

Kool Aid with a touch of vodka
Joined
Feb 5, 2003
Posts
29,476
Reaction score
16,649
Location
San Antonio, Texas
It is a sight to see

Talking about strange. Had a exhibition at my Gallery in Denver so I had a stop in Phoenix on my way to CO. Saw the Cardinal team jet off to the side while landing. Completely wierd, saw Dave McGinnis at the airport (what he was doing there I have no idea and maybe I was mistaken but he did give me a double take...only Texan in the terminal with Cardinal gear on). On my way back from Denver saw the new stadium from above and it brought cardinal bumps all over me. GO CARDINALS!

Great pics!!! :thumbup:
 

azdad1978

Championship!!!!
Joined
Dec 8, 2002
Posts
14,982
Reaction score
50
Location
ordinance 2257
Stop by there around 6:40 PM and amazed with what I saw. All I could say is Wow. Btw anybody notice around the Glendale arena that some part of the arena that is empty lots have fences on them? Does that mean they will start construction on Westgate??? btw nice pics az-red :thumbup:
 

TruColor

Trombonist in Roger Goodell's Wedding Rcpt.
Joined
May 13, 2002
Posts
4,148
Reaction score
3,097
Location
Prescott, AZ
azdad1978 said:
Stop by there around 6:40 PM and amazed with what I saw. All I could say is Wow. Btw anybody notice around the Glendale arena that some part of the arena that is empty lots have fences on them? Does that mean they will start construction on Westgate??? btw nice pics az-red :thumbup:

Westgate already has some construction photos up on their site:

http://www.westgateaz.com/
 

Latest posts

Forum statistics

Threads
553,682
Posts
5,410,699
Members
6,319
Latest member
route66
Top