Slingshot Photography provided photos of the Stadium Roof lift that occurred from Feb. 18-21, 2005.
On Friday, the process of disconnecting the Brunel truss from the yellow jacks that supported the roof during construction began.
By Saturday mid-morning, the roof was already lifted several feet above the yellow jacks.
View from field level of the roof lift on Saturday afternoon.
The roof will eventually be raised all the way to the top of the four Super Columns.
Shot of stadium late afternoon on Saturday.
Panned view of stadium, taken on Saturday afternoon.
On Sunday, Mammoet (lifting contractor) decided to replace some of the lifting wedges, halting the progress of the roof lift. This picture, taken at sunrise on Monday shows the additional 53 feet that the roof needed to be raised to.
Later on Monday, the roof nears its completion point.
Slingshot Photography provided photos of the Stadium Roof lift that occurred from Feb. 18-21, 2005.
On Friday, the process of disconnecting the Brunel truss from the yellow jacks that supported the roof during construction began.
You must be registered for see images
By Saturday mid-morning, the roof was already lifted several feet above the yellow jacks.
You must be registered for see images
View from field level of the roof lift on Saturday afternoon.
You must be registered for see images
The roof will eventually be raised all the way to the top of the four Super Columns.
You must be registered for see images
Shot of stadium late afternoon on Saturday.
You must be registered for see images
Panned view of stadium, taken on Saturday afternoon.
You must be registered for see images
On Sunday, Mammoet (lifting contractor) decided to replace some of the lifting wedges, halting the progress of the roof lift. This picture, taken at sunrise on Monday shows the additional 53 feet that the roof needed to be raised to.
You must be registered for see images
Later on Monday, the roof nears its completion point.
You must be registered for see images